Network Core Availability
The year so far - 2012
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sept | Oct | Nov | Dec |
| 100% | 100% | 100% | 100% |
Availability Comments
April: n/a - no jobs completed this month
March:
FEBRUARY: Cabling installations:
32 jobs closed during January & February 2012, taking an average of 16 working days.
75% of jobs were with ITS for less than 5 days and Estates managed to process 18% within 5 days.
JANUARY: No figures are available to date